<?xml version="1.0" encoding="utf-8"?>
<feed xmlns="http://www.w3.org/2005/Atom" xml:lang="en"><title>Standby Atlas: data-centre filings naming Baudouin</title><link href="https://standbyatlas.com/alerts/"/><link rel="self" href="https://standbyatlas.com/alerts/make/baudouin.xml"/><id>https://standbyatlas.com/alerts/make/baudouin.xml</id><updated>2026-11-09T00:00:00Z</updated><author><name>Standby Atlas</name></author><entry><title>Virtus Holdco Limited data centre in Saunderton, United Kingdom: Environmental permit application</title><link href="https://standbyatlas.com/projects/gb-bkm-saunderton-virtus-lon15-18/"/><id>tag:standbyatlas.com,2026:gb-bkm-saunderton-virtus-lon15-18:2026-04-23</id><updated>2026-04-23T00:00:00Z</updated><summary>Environmental permit application on 23 Apr 2026. 57 backup generators. 356.2 MW of thermal input. Engine makes named: Baudouin. Source: Environment Agency.</summary></entry></feed>