OVHcloud data centre in Gravelines, France

Latest document dated 28 Oct 2025, from Mission régionale d'autorité environnementale (MRAe). Official document

Location of the project in Europe. Grey dots: other projects in the index.
backup generators
69
MW of generator thermal input
185

The backup fleet in the filing

Each block is one generator set: 69 in all.

Timeline

Public documents for this project, and what our daily checks found.

  1. Environmental-authority opinion (MRAe)

    Mission régionale d'autorité environnementale (MRAe). Official document

  2. Official document online at our check

    Checked every day since 9 Nov 2026.

  3. Licence Display windows, objection deadlines and every amendment, with page references

The record

Standby Atlas recordFR-HDF-GRAVELINES-OVHCLOUD
Location
Gravelines, France
Operator or project company
OVHcloud
Stage
Environmental-authority opinion (MRAe)
Filing date
28 Oct 2025
IT load
Not stated in the filing
Grid connection
Not stated in the filing
Backup generators
69
Generator thermal input
185 MW
Engine makes named
Not named in the filing

Source: Mission régionale d'autorité environnementale (MRAe). Checked on 9 November 2026.

This record as JSON

What the licences add for this project

Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.

Follow new filings

Free Atom feeds, updated with each monthly release.