Environmental permit granted

Amazon Data Services UK Limited data centre in Didcot, United Kingdom

Latest document dated 27 Jul 2026, from Environment Agency. Official document

Location of the project in Europe. Grey dots: other projects in the index.
backup generators
129
MW of generator thermal input
925

The backup fleet in the filing

Each block stands for five generator sets: 129 in all.

Timeline

Public documents for this project, and what our daily checks found.

  1. Environmental permit granted

    Environment Agency. Official document

  2. Official document online at our check

    Checked every day since 9 Nov 2026.

  3. Licence Display windows, objection deadlines and every amendment, with page references

The record

Standby Atlas recordGB-OXF-DIDCOT-AMAZON-NORTH
Location
Didcot (ancienne centrale Didcot A), United Kingdom
Operator or project company
Amazon Data Services UK Limited
Stage
Environmental permit granted
Filing date
27 Jul 2026
IT load
Not stated in the filing
Grid connection
Not stated in the filing
Backup generators
129
Generator thermal input
925 MW
Engine makes named
Not named in the filing

Source: Environment Agency. Checked on 9 November 2026.

This record as JSON

What the licences add for this project

Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.

Follow new filings

Free Atom feeds, updated with each monthly release.