Industrial-emissions licence application
Amazon Data Services Ireland Limited data centre in Baldonnell, Ireland
Latest document dated 6 Jul 2023, from Environmental Protection Agency (Ireland). Official document
- backup generators
- 73
- MW of generator thermal input
- 460.9
The backup fleet in the filing
Timeline
Public documents for this project, and what our daily checks found.
- Industrial-emissions licence application
Environmental Protection Agency (Ireland). Official document
- Official document online at our check
Checked every day since 9 Nov 2026.
- Licence Display windows, objection deadlines and every amendment, with page references
The record
Standby Atlas recordIE-DUB-BALDONNELL-AMAZON-P1170
- Location
- Baldonnell (Grange Castle South Business Park, Baldonnel Road), Ireland
- Operator or project company
- Amazon Data Services Ireland Limited
- Stage
- Industrial-emissions licence application
- Filing date
- 6 Jul 2023
- IT load
- Not stated in the filing
- Grid connection
- Not stated in the filing
- Backup generators
- 73
- Generator thermal input
- 460.9 MW
- Engine makes named
- Not named in the filing
Source: Environmental Protection Agency (Ireland). Checked on 9 November 2026.
What the licences add for this project
Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.
Other projects in Ireland
- 58generatorsHuntstown Power Company Limited data centre in Finglas, IrelandPlanning permission granted on appeal, 27 Feb 2025
- 54generatorsAmazon Data Services Ireland Ltd data centre in Drogheda, IrelandIndustrial-emissions licence application, 1 Sep 2025
- 39generatorsUniversal Developers LLC data centre in Dublin 15, IrelandPlanning permission granted on appeal, 19 Dec 2025
- 24generatorsEdgeConneX Ireland Limited data centre in Lucan, IrelandPlanning permission granted on appeal, 31 Jul 2025
- 21generatorsMicrosoft Operations Ireland Ltd. data centre in Clondalkin, IrelandPermit extended, 21 Jul 2026
- 15generatorsAmazon Data Services Ireland Limited data centre in Leixlip, IrelandRefused or not admitted, 17 Oct 2025