Free sample

Application filed

VDC MXP11 S.r.l. data centre in Melegnano, Italy

Latest document dated 19 Mar 2024, from Ministero dell'Ambiente e della Sicurezza Energetica. Official document

Location of the project in Europe. Grey dots: other projects in the index.
MW of generator thermal input
293

The backup fleet in the filing

The filing does not state how many generator sets there are.

Timeline

Public documents for this project, and what our daily checks found.

  1. Application filed

    Ministero dell'Ambiente e della Sicurezza Energetica. Official document

  2. Official document online at our check

    Checked every day since 9 Nov 2026.

  3. Licence Display windows, objection deadlines and every amendment, with page references

The record

Standby Atlas recordIT-LOMB-MELEGNANO-VANTAGE-MXP1
Location
Melegnano (ambito di trasformazione AT 24), Italy
Operator or project company
VDC MXP11 S.r.l.
Stage
Application filed
Filing date
19 Mar 2024
IT load
Not stated in the filing
Grid connection
Not stated in the filing
Backup generators
Not stated in the filing
Generator thermal input
293 MW
Engine makes named
Not named in the filing

Source: Ministero dell'Ambiente e della Sicurezza Energetica. Checked on 9 November 2026.

This record as JSON

What the licences add for this project

Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.

Follow new filings