EIA scoping notice
Microsoft Datacenters Netherlands B.V. data centre in Middenmeer, Netherlands
Latest document dated 30 Dec 2025, from Officiële bekendmakingen. Official document
- backup generators
- 126
The backup fleet in the filing
Timeline
Public documents for this project, and what our daily checks found.
- EIA scoping notice
Officiële bekendmakingen. Official document
- Official document online at our check
Checked every day since 9 Nov 2026.
- Licence Display windows, objection deadlines and every amendment, with page references
The record
Standby Atlas recordNL-NH-MIDDENMEER-MICROSOFT-AMSE-B1
- Location
- Middenmeer (Agriport), Netherlands
- Operator or project company
- Microsoft Datacenters Netherlands B.V.
- Stage
- EIA scoping notice
- Filing date
- 30 Dec 2025
- IT load
- Not stated in the filing
- Grid connection
- Not stated in the filing
- Backup generators
- 126
- Generator thermal input
- Not stated in the filing
- Engine makes named
- Not named in the filing
Source: Officiële bekendmakingen. Checked on 9 November 2026.
What the licences add for this project
Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.