Environmental permit granted

SI STO 01.2 AB data centre in Upplands Väsby, Sweden

Latest document dated 11 May 2023, from Naturvårdsverket. Official document

Location of the project in Europe. Grey dots: other projects in the index.
backup generators
20
MW of generator thermal input
58.1

The backup fleet in the filing

Each block is one generator set: 20 in all.

Timeline

Public documents for this project, and what our daily checks found.

  1. Environmental permit granted

    Naturvårdsverket. Official document

  2. Licence Display windows, objection deadlines and every amendment, with page references

The record

Standby Atlas recordSE-AB-UPPLANDSVASBY-SISTO012
Location
Upplands Väsby (Älvsunda 7:10), Sweden
Operator or project company
SI STO 01.2 AB
Stage
Environmental permit granted
Filing date
11 May 2023
IT load
Not stated in the filing
Grid connection
Not stated in the filing
Backup generators
20
Generator thermal input
58.1 MW
Engine makes named
Not named in the filing

Source: Naturvårdsverket. Checked on 9 November 2026.

This record as JSON

What the licences add for this project

Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.